A building that has a long history behind it like Palazzo Ferlendis , which, now for six hundred years, stands on the banks of the splendid Lake of Iseo , is certainly loaded with a timeless charm but does not transcend, like any property, the inevitable signs of age. The situation that we at Schiavi Spa we were faced with the moment we started his recovering project was, objectively, critical: the building had a clear weakening, and the walls at the level of the foundations showed ** localized phases**. It was therefore urgent to intervene in a timely way to remedy the problems that had accumulated over time. As already described in our previous articles on the topic, Palazzo Ferlendis originally placed itself directly on the shores of the lake. Several successive urbanistic interventions had caused a backwarding of the lake, giving rise to a square in front of the shore and modifying the structure of the entire area. These changes in the composition of the ground inevitably affected the static behaviour of the Palace, causing a sinking and a sliding of the foundations towards the water.
To put an end to this objective and serious criticality** we have planned a ** structural consolidation intervention** made through the technique of the ..micropals
Once we had secured the palace's footpaths we went to the
We then intervened by emptying the vaults at the end of the extradone**, thus releasing them from the weight of the filling materials, and then clothing them with a metal armor**. At the level of the extradone we then created a system of concrete beams to support the loads that had been burdened up to that time. The latter were later 'appended to the beams themselves, conjuring any risk of collapse. Once secured the vaults, we finally proceeded to their restoration intradox while recovering the original paintings. Only then did we begin to deal with the murs on the upper floors. The stone walls also needed a measure. We then removed the plaster to bring the stone to light and intervene directly on it. The stone wall was thus
A different situation was found at the level of the ground floor and second floor gates**: here, most of the loads grave in fact on slender stone columns. To remove the weight and share the loads more evenly, the columns were flanked by metal pillars which allowed the complete safety of these areas of the Palace. The whole of the interventions to be carried out on the ** walls of Palazzo Ferlendis** presented itself, since the preliminary inspection phase, extremely complex and articulated**. However, thanks to the collaboration between various professionals, all coordinated by Schiavi Spa, the operations were carried out in a manner of art and the old historical building recovered a solidity that seemed lost forever.
To view videos, enable external content in your cookie preferences.


.ngO8nVNv_iLTP4.webp)